Jellinbah Group Pty Ltd & Ors v Chief Executive, Department of Environment, Science and Innovation [2024] QLC 15

Item

Title
Jellinbah Group Pty Ltd & Ors v Chief Executive,
Department of Environment, Science and Innovation [2024]
QLC 15
Date
August 2, 2024
Court or Tribunal
Decision Maker
HRA Sections
Summary
An application to the court for a Progressive Rehabilitation and Closure Plan (PRCP).

The court referred to a five-step process for applying human rights, under s 58 of the Human Rights Act. After accepting the respondent's submissions that no relevant rights would be impacted by approving the amended schedule, the court found it did not need to consider the remaining four steps.