Rolleston Coal Holdings Pty Ltd v Department of Environment, Tourism, Science and Innovation
[2025] QLC 22
Item
-
Title
-
Rolleston Coal Holdings Pty Ltd v Department of Environment, Tourism, Science and Innovation
[2025] QLC 22
-
Date
-
September 5, 2025
-
Summary
-
This case concerned objections to Rolleston Coal Holdings Pty Ltd’s application to amend an environmental authority under the Environmental Protection Act 1994 (Qld) for the expansion of operations at the Rolleston Coal Mine. The objectors, Environmental Advocacy in Central Queensland Inc and Lock the Gate Alliance Ltd, opposed the amendment on the basis that it would contribute to climate change and therefore be inconsistent with the Human Rights Act 2019 (Qld). They argued that the emissions from the project would adversely affect the right to life (section 16) and the protection of families and children (section 26(1)). Accordingly, granting the amendment would be incompatible with these rights.
The Land Court of Queensland, constituted by Member McNamara, acknowledged its obligations under section 58 of the Human Rights Act 2019 (Qld) as a public entity to make decisions in a way that is compatible with human rights and to give proper consideration to any relevant human right: at [237] - [244]. The Court noted that the right to life (section 16 of the Human Rights Act 2019 (Qld)), the right to protection of families (section 26(1)) , and the right to recognition and equality before the law (section 15(1)) were potentially limited by the environmental consequences of the proposed amendment: at: [240], [268].
The statutory party accepted that these rights were engaged but submitted that any limitation arising from the decision to approve the amendment was minimal and consistent with Queensland’s legislative and policy framework governing greenhouse gas emissions and climate change: at [240] - [248]. It was argued that the mine’s contribution to global emissions was relatively small in the context of total state and national emissions and that the applicant's Human Rights Management Plan provided appropriate mechanisms for assessment and mitigation as well as an avenue for human rights complaints to be raised and investigated: at [245]-[246].
The Court ultimately concluded that if any human rights were engaged here, any limitations upon those rights were appropriate and proportional: at [268], [290]. The objections were dismissed, and the Court recommended that the amendment to the environmental authority be approved.